A Stage-Gate Process for Small Companies: What to Keep and What to Scale Down

How do we put discipline into product development without a heavy process we cannot staff?

ResearchGate · Robert G. Cooper

Published Updated

Stage-Gate is a gated roadmap from idea to launch, and Robert G. Cooper says it is not a fixed rulebook. The work that matters most is the homework before heavy spending, especially the written product definition at Gate 3. Stages can be left out and gates combined for lower risk projects, if the choice is made on purpose at a gate. A small company can keep the gates and the must-meet checklist, and route small projects through a shorter path.

Where a small team loses time and money

A small engineering team often starts a project because someone has a good idea and the capacity to try it. The trouble shows up later. The market work was thin, the product was never defined in writing, and heavy spending began before anyone checked the basics. Fixing the problem at that point is expensive.

Robert G. Cooper built the Stage-Gate system to prevent this. His introductory paper describes it as a roadmap for moving a project from idea to launch, with best practices built into the steps. The question for a company of 50 to 200 people is how much of it to adopt. Cooper's answer is that the system is not a fixed rulebook. This article follows his paper to show which parts carry the weight and which parts can shrink.

What the system is

Stage-Gate splits a project into stages and puts a gate in front of each one. A stage is a set of prescribed tasks, done at the same time by people from several functions. A gate is a meeting where managers decide whether the project goes on.

Cooper compares it to football. The stages are the plays. The gates are the huddles, where the team stops and pulls its new information together.

Two features shape how it works.

  • Every stage is cross-functional
    • Cooper says there is no engineering stage or marketing stage. Every stage involves engineering, marketing, operations and others, working in parallel.
  • Each stage costs more than the one before it
    • Spending rises in steps while the unknowns fall. Cooper calls this a risk-mitigating model, because money is committed only as the uncertainty drops.

He also says the tidy sequence on the page is not how projects run. There is a lot of iteration and circling back, within stages and often between them.

The stages and what each is for

Cooper's standard model for a major project has an ideation step and five stages.

  1. Discovery. Work to find opportunities and ideas. Cooper notes that a good process cannot make up for a shortage of good ideas. The output is a one-page description of the idea.
  2. Scoping. Quick desk research on the market, the technology and the business. Cooper says it often takes under a month and 5 to 20 person-days.
  3. Build the Business Case. A detailed investigation with primary research. It covers voice of the customer, competitors, concept testing, technical and operations appraisals, and a financial analysis with sensitivity checks.
  4. Development. The design and build of the product, with build, test, feedback and revise cycles. It ends with an internally tested prototype.
  5. Testing and Validation. Lab tests, field or beta trials, pilot production, and a revised financial analysis.
  6. Launch. Full production, marketing and selling.

A post-launch review follows, often 6 to 18 months later. Actual results are compared with the projections made at Gates 3 and 5, and the team records what to do better next time.

How a gate works

Each gate has the same three parts.

  • Deliverables
    • What the team must bring to the meeting. They come from a standard menu for that gate, usually as templates, and are set at the previous gate. Management's expectations are visible.
  • Criteria
    • A must-meet checklist of knock-out questions, such as whether the project fits the business mandate and meets environmental, health and safety policy. A should-meet scorecard covers factors such as the strength of the value proposition, use of core competencies, market attractiveness, and return against risk.
  • Outputs
    • A decision of Go, Kill, Hold or Recycle. On a Go, an approved plan for the next stage with people, money and person-days, a timeline, and the deliverables and date for the next gate.

The early gates are light. Cooper calls Gate 1 a gentle screen on qualitative criteria, with no financial test because there is too little information. Gate 2 repeats it with a quick financial check, such as payback period.

Gate 3 is the last point where the project can be killed before heavy spending. It also signs off the product and project definition. The gatekeepers are the managers who own the resources the next stage needs.

Why Stage 2 needs the most care

Cooper calls Build the Business Case a make-or-break stage. He says most new product failures trace back to it, and that benchmarking studies keep citing it as weakly executed.

The reasoning is simple. The product definition is written here, and it is a required deliverable for Gate 3. Without it the project cannot enter Development. A team eager to start building may be tempted to shorten this work. Cooper's paper argues that this is where the homework pays off.

How to scale it down

Cooper is clear that one size does not fit all. A smaller, lower risk project does not need the same work and scrutiny as a larger one.

His rule is that stages can be left out and gates combined, provided the decision is made on purpose, at a gate, with a full understanding of the risk. He describes the whole system as a risk-management system. The risk level and the need for information decide which steps are done.

The shortened version is Stage-Gate XPress, with three stages and three gates. Cooper reserves it for lower risk work such as extensions, fixes, improvements and product renewals. The routing decision is made at the previous gate, often as early as Gate 1. A two-stage version serves very minor developments.

He gives an example from a large bank that sorts projects into three groups by scope, investment and risk.

  • System change requests
    • Minor changes and improvements. They go through two stages and two gates.
  • Fast track projects
    • Medium cost projects with some risk, under $500,000 in development cost. They go through four stages, with the two homework stages merged into one.
  • Major projects
    • Over $500,000, and higher risk. They go through the full five stages.

The thresholds are the bank's. A small manufacturer would set its own line, based on its own budgets and risk.

Iteration and Agile methods

Cooper describes Stage-Gate as adaptive. Versions of the product are built quickly and shown to customers, on the idea that customers often do not know what they want until they see it.

He also reports that leading firms combine Agile methods with Stage-Gate. The sprints are short, typically 2 to 4 weeks, and they produce something that can be demonstrated. The combination often starts in Development and Testing. Cooper treats the two as complementary rather than as substitutes.

Take-homes for a small manufacturer

  • Write the product definition down before heavy spending
    • Cooper makes it a deliverable at Gate 3. It sets scope and requirements at the start.
  • Keep a short must-meet checklist
    • A few knock-out questions remove misfit projects early and cheaply.
  • Define gate deliverables as templates
    • The team then knows what the decision meeting expects.
  • Sort projects by risk at an early gate
    • Route low risk work through a shortened path, and keep the full path for larger bets. Make each omission a deliberate decision.
  • Treat Recycle and Hold as normal outcomes
    • Cooper expects iteration, and a gate can send a project back for more information.
  • Hold the post-launch review
    • Compare results with the Gate 3 and Gate 5 projections, and record the lessons.