Design for Manufacturing: A Checklist to Run Before Every Design Review
How do we design a part so it is easier and cheaper to build, and what should we check before a design review?
Published Updated
Benedict O'Neill's guide on Wevolver says design decisions set most of a part's manufacturing cost, citing Boothroyd Dewhurst for about 80 percent, and that a change after tooling can cost 10 to 100 times more than one at concept. It reduces design for manufacturing to five principles, treats tolerances as a cost multiplier, and gives design rules for injection molding, CNC machining, sheet metal, and additive manufacturing. Its advice is to pick the process first, default to general tolerances, tighten only functional features, bring suppliers in early, and run a checklist before every design review. Its numeric rules come from supplier guidelines, so confirm them with the shop that builds your part.
Why design decides the cost
A part is cheap or costly long before anyone cuts metal. The design sets what the process has to do.
This article summarizes a guide by Benedict O'Neill, published on the engineering site Wevolver and last updated August 10, 2026. The guide cites Boothroyd Dewhurst, the developers of the design for manufacturing and assembly method. Boothroyd Dewhurst holds that about 80 percent of manufacturing cost is set by design decisions. A change that costs almost nothing at concept stage can cost 10 to 100 times more after tooling is cut.
The guide gives design rules for four processes: injection molding, CNC machining, sheet metal, and additive manufacturing. This summary covers those four. The numeric rules are the guide's, drawn from supplier design guidelines. Treat them as starting points and check them with your own supplier.
What design for manufacturing means
The guide defines it as three practices.
- Choose the process
- Match the manufacturing process to the part, the material, and the production volume.
- Shape the part for that process
- Wall thickness, draft angles, radii, feature sizes, and tool access all follow from the process.
- Specify no tighter than function needs
- Materials, tolerances, and finishes should be no tighter than the function requires.
The guide says DFM belongs inside the development process, not after it. The engineer who releases the drawing and the one who builds the part see different limits. DFM is the shared language that settles them while changes are cheap.
DFM, DFA, and DFMA
The terms overlap, and the guide separates them.
- DFM
- It looks at individual parts and their processes. Can this be molded, machined, bent, or printed efficiently?
- DFA
- It looks at the whole product and its assembly. How many parts are there, and how long does assembly take?
- DFMA
- It applies both as a formal method.
In the Boothroyd Dewhurst method, a separate part earns its place only if it meets one of three tests. It moves relative to its neighbor, it must be a different material, or it must be separate to allow assembly or service. The guide notes that DFA comes before DFM. You decide whether a part needs to exist before you optimize how it is made.
Why it matters beyond cost
The guide says DFM is usually sold as cost reduction, but it also affects time and quality.
- Cost
- A thick section in a molded part extends cooling time and raises the piece price on every unit. A sharp internal corner in a machined pocket forces a smaller cutter.
- Time to market
- Parts designed within process limits get quoted, tooled, and approved faster.
- Quality
- The guide says most chronic defects, such as sink marks and warpage, are designed in.
Five principles
The guide reduces DFM to five principles and suggests using them as the outline of a design review.
- Process selection. Injection molding spreads tooling over tens of thousands of units. CNC machining suits low volumes and high precision. 3D printing suits complex shapes at very low volumes.
- Design for the process. Follow its rules once it is chosen.
- Material selection. Choose for function and for processability. The cheapest material per kilogram is not always the cheapest part.
- Environment. Design for temperature, chemicals, vibration, and light in service.
- Compliance and testing. Build in regulatory requirements, and make inspection easy.
Standardization runs through all five. Standard fasteners, stock sizes, and tolerance classes simplify buying and assembly.
Tolerances are a cost multiplier
The guide calls tolerancing the place where good design can turn into expensive manufacturing. Each tighter tolerance means slower feeds, extra operations such as grinding or reaming, more scrap, and more measurement time. Each step tighter costs more than the last.
The guide gives three rules.
- Default to general tolerances
- ISO 2768 sets general tolerance classes: f for fine, m for medium, c for coarse, and v for very coarse. A title block note such as ISO 2768-mK covers the whole drawing.
- Tighten only functional features
- Bearing seats, sealing faces, and mating interfaces get explicit tolerances. Cosmetic surfaces do not.
- Use GD&T for complex parts
- ASME Y14.5 sets the symbols, datums, and rules.
The guide shows the ISO 2768 limits on linear dimensions. For sizes from 6 to 30 mm, the classes allow plus or minus 0.1, 0.2, 0.5, and 1.0 mm. For 30 to 120 mm, they allow plus or minus 0.15, 0.3, 0.8, and 1.5 mm.
It also compares a drawing with what a process can hold. Protolabs holds a machining tolerance of plus or minus 0.08 mm on a mold, plus a resin tolerance of at least 0.002 mm per mm on the part. A molded part drawn at plus or minus 0.02 mm over 100 mm asks for something the process cannot give.
Ask two questions of every tight tolerance. What failure does it prevent, and what will it cost to verify? If the first has no clear answer, relax the tolerance. A stack-up analysis across the assembly shows which dimensions need control. The guide calls tightening everything to be safe the most common self-inflicted cost overrun in mechanical design.
Design rules by process
The same bracket designed for four processes should look like four different parts, the guide says.
Injection molding
- Walls
- Keep them uniform and inside the resin's range to avoid sink marks, voids, and warpage. The guide lists ABS at 1.14 to 3.56 mm and PC at 1.02 to 3.81 mm, with other resins in its table.
- Draft
- Use at least 0.5 degrees on faces parallel to the mold opening, with 2 degrees typical. Textured surfaces need 3 to 5 degrees or more.
- Ribs and bosses
- Use ribs instead of thicker walls, at 40 to 60 percent of the nominal wall. Support bosses with ribs or gussets.
- Undercuts
- Avoid them where you can. They raise tooling cost and cycle time.
CNC machining
- Internal corners
- Make the radius at least the cutter radius, or one fifth of the wall height, whichever is greater. Larger radii allow bigger tools and faster work.
- Standard tools
- Match radii to standard tooling. The guide suggests ball end mill sizes of 3, 6, 8, 10, and 12 mm.
- Walls and holes
- Keep wall thickness at least one eighth of wall height. Keep holes up to 8 times their diameter deep when 12.7 mm or under, and up to 4 times above that.
- Pockets and setups
- Deep narrow pockets multiply time and tool breakage risk. Each extra setup adds handling and tolerance risk, so use as few faces as you can.
- Default tolerance
- Where nothing is specified, expect about plus or minus 0.13 mm.
Sheet metal
- Thickness
- Standard fabrication runs from about 0.6 to 6.35 mm. Use one thickness per part.
- Bends
- Use standard radii of 0.76, 1.52, 2.29, or 3.05 mm and keep them consistent. Expect about plus or minus 1 degree on bend angles.
- Flanges and holes
- Make flanges at least 4 times the thickness. Keep holes and slots at least 4 times the thickness from a bend, or they will deform.
Additive manufacturing
- Walls
- Use at least 0.8 mm across processes, and more for structural features.
- Overhangs
- FDM and SLA generally handle about 45 degrees from vertical before supports are needed. SLS needs no dedicated supports.
- Consolidation
- Combine assemblies into single printed parts where you can.
For circuit boards, the guide says to respect the fabricator's limits and run its DFM checks before release.
Running DFM in practice
The guide calls DFM a workflow more than a rule set.
- Start at concept
- Pick candidate processes and target volumes before detailed design.
- Involve manufacturing early
- Bring in manufacturing engineers and suppliers from the first prototype. The guide says suppliers know their machines' real capability better than any handbook.
- Use your CAD tools
- Draft analysis, thickness analysis, and DFM checkers catch problems while they are free to fix.
- Run failure analysis
- A design FMEA finds failure modes early. A process FMEA does the same for the production line.
- Get quotes early
- Instant-quote platforms return automated DFM feedback in hours, even if production goes elsewhere.
- Keep the record
- Store drawings, revisions, and supplier feedback in one system.
The checklist
The guide offers a checklist to run before every design review. Each no is either a redesign task or a documented, justified exception. It covers six groups.
- Process and volume
- Is tooling and piece price modeled at the target volume, and at half and double it?
- Material
- Is it available in standard grades and forms from more than one supplier?
- Part geometry
- Does the part meet the rules for its process?
- Tolerances and drawings
- Is there a general tolerance class on the title block, with explicit tolerances only on functional features?
- Assembly
- Does every part justify its existence, and does each assemble from one direction?
- Validation
- Has supplier feedback been reviewed, and is there an inspection method for every tight tolerance?
Common mistakes
The guide names four.
- Tolerancing by fear
- Base tolerances on stack-up analysis, not on a wish to be safe.
- The process-agnostic part
- A part that could be molded or machined is optimized for neither.
- Custom everything
- Custom fasteners, radii, and stock sizes add cost and risk with no payoff in function.
- DFM at the end
- A review right before production will not recover lost expense.
What to take from it
- Review early
- Run DFM at concept, while the process and volume are still open.
- Pick the process first
- Then follow its rules, and do not draw a part that suits two processes poorly.
- Put a general tolerance class on the drawing
- Add explicit tolerances only where function needs them, and ask what each one costs to verify.
- Ask the supplier
- Treat published numbers as starting points and confirm them with the shop that will build the part.
- Question every part
- If it does not move, change material, or allow assembly or service, ask whether it needs to exist.
- Use the checklist as a gate
- Every no becomes a task or a written exception.
References
- O'Neill, Benedict. Design for Manufacturing (DFM): The Engineer's Complete Guide. Wevolver. Last updated August 10, 2026. https://www.wevolver.com/article/design-for-manufacturing-dfm-the-ultimate-guide-to-streamlining-product-development-and-reducing-costs